Previous: 2002
- Completed
$125,000 plus Clinton County Pectil drain
Installed 24”, 18”, and 15” N-12
pipe & bored over 2 miles under 2 paved roads
Provided “as built” GPS data for
county records
- Completed
$90,000 Ionia County main
Open ditch, 24”, 18”, 15”, and 12”
ND.
Project length was 1½ miles
Exciting on this project was
installing 600 feet of 18” N-12 20 feet deep less than 3 feet away & 2 feet
deeper than existing concrete pipe
- Installed
over 1.5 million feet of 3”, 4”, 6”, 8”, & 12” for farm drainage
Previous: 2003
- Completed
$200,000 Jennings county drain system for Newaygo County
Replaced almost 2 miles of 24”,
18”, 15” and 12” N-12 pipe, including catch basins, paved road crossings,
constructing retention ponds, and maintaining wooded areas.
- Completed
$180,000 inter-county drain #134 between Clinton & Gratiot County
- Reconstructed
drains in the Lake Victoria Subdivision, an unique project as work was
between existing homes and design required slowing down discharge water
into Lake Victoria
Replaced over 2 miles of 30” down to
15” N-12 pipe including overflow ditches, catch basins and road crossings.
- Installed
1.2 million feet of tile for farm drainage
2004 projects
·
Nearly 1 mile of reconstructing 2 different
county drains for Ionia County, and bidding on other county drain projects
·
Maintaining our quality service to our farm
customers
2005
projects
·
Formed Advanced Geo Positioning Solutions Inc.
for automated GPS machine control for drainage, construction, ditching, and
land leveling applications, selling 2 complete systems
·
Installed over 7000 feet of N-12 pipe for Ionia
County & managed 4 miles of open ditch construction
·
Installed 1.4 million feet for farm drainage
2006
projects
- Installed over 2 miles of N-12 pipe for
county drains
- Server our farm drainage market
installing 1.4 million feet of drainage tile
- Sold & installed 5 AGPS systems
- Began service to Michigan Land
Improvement Contractors as Executive Director
2007 projects
- Installed 1.9 million feet of Drainage
pipe for our farm customers, our best year ever, not possible without my
crew
- installed 300o feet of N-12 for county
drains
- sold & installed 4 AGPS systems
- hosted the MLICA field day at Cook
Brothers Farms near Vermontville Mi.
Designed & Coordinated the Event
2008 forecast
- Will take delivery of a new Bron 360
drainage plow..the first of its kind.
This machine will counter-rotate 180 degrees like an excavator
- Will again host the MLICA field day
across the road from last years event.
Cook Brothers will show the results from last years installation.
-
Back to top